Sourcing and Supply Chain

When is Chinese New Year 2027? A Planning Guide for UK Manufacturers

If your parts come from China or elsewhere in Asia, the weeks before Christmas are the time to plan for Chinese New Year. This guide covers the key dates for 2027, how long factories are affected, and what to check now.

By Dr Mohammad Musameh, BEng (Hons), PhD, FHEA, MIET, founder of MGS Components. Mohammad has a background in electrical and electronic engineering and over a decade of experience across engineering, product development and international sourcing.

Quick answer

Chinese New Year 2027 falls on Saturday 6 February, 11 days earlier than in 2026. China's official holiday runs from Friday 5 to Saturday 13 February. The festival is also celebrated in Vietnam, Taiwan, South Korea and other parts of Asia, where it's often called Lunar New Year, so suppliers there may close too.

However, delays to your parts last much longer than the holiday itself. Many factories slow down from mid-January, and parts ordered in March may not reach the UK until late May.

It's worth planning for both Q1 and Q2 of 2027. Before Christmas, check your parts list, your suppliers' closing and reopening dates, and how long your stock will last.

When is Chinese New Year 2027?

Chinese New Year's Day is Saturday 6 February 2027. China's official holiday runs for nine days, from New Year's Eve on Friday 5 February to Saturday 13 February. To make up the time off, factories and offices work two extra Sundays, one before the holiday and one after.

China's State Council confirmed the dates on 5 November 2026 (China Briefing, 6 November 2026).

Chinese New Year isn't only celebrated in China, so suppliers in other countries close too. The table below shows the key dates for 2027 in China, Vietnam, Taiwan and South Korea.

Key Lunar New Year dates for 2027 in China, Vietnam, Taiwan and South Korea
Date (2027)What happensWhere
Sunday 31 JanuaryMake-up working dayChina
Thursday 4 to Wednesday 10 FebruaryLunar New Year (Tết) holiday, official datesVietnam
Thursday 4 to Wednesday 10 FebruaryLunar New Year holiday, government calendarTaiwan
Friday 5 to Saturday 13 FebruarySpring Festival public holiday (nine days)China
Saturday 6 FebruaryChinese New Year's DayChina, Vietnam, Taiwan and other countries
Saturday 6 to Tuesday 9 FebruarySeollal (Lunar New Year) holidaySouth Korea
Sunday 14 FebruaryMake-up working dayChina
Saturday 20 FebruaryLantern Festival, the end of the New Year periodChina and other countries

In Vietnam, these are the official dates for government workers. Private companies can pick slightly different dates, so factory closures there may vary (Vietnam Briefing). Taiwan's dates come from its 2027 government calendar (Human Resources Online). Individual factories may set their own dates, so it's best to ask each supplier.

Is Chinese New Year the same as Lunar New Year?

In most cases, yes. Chinese New Year is the name most people in the UK use, but the festival is celebrated well beyond China, which is why it's also known as Lunar New Year. It's called the Spring Festival in China, Tết in Vietnam and Seollal in South Korea.

It's a public holiday in Taiwan, Hong Kong, Singapore and Malaysia too. Breaks outside mainland China, Vietnam and Taiwan are usually shorter, from two days in Malaysia to four in South Korea and Hong Kong. The date can also differ by a day, and in 2027 South Korea's Seollal falls on 7 February (SEKO Logistics, 6 August 2026).

If your parts come from more than one country in Asia, several of your suppliers may close at the same time. It's worth checking each one's dates rather than planning around China alone.

Why does Chinese New Year 2027 need earlier planning?

For UK manufacturers buying parts from China or elsewhere in Asia, an earlier holiday means earlier deadlines. Your orders need to be placed, made and shipped sooner than usual, and much of that work now falls over the UK Christmas break, leaving fewer working days to get it done.

Every step in getting parts to your factory has to happen earlier, from placing the purchase order to catching the last ship before the holiday (SEKO Logistics, 28 October 2026). Space on ships also gets harder to book in the weeks before the holiday, as exporters rush to send goods out before factories close.

At the same time, your own team and many of your UK and European suppliers will be off for Christmas. UK bank holidays fall on Friday 25 December, Monday 28 December and Friday 1 January, with an extra day in Scotland (GOV.UK), and many businesses close or run reduced hours between Christmas and New Year.

Some of your suppliers in China may not have set their own closing dates yet, as the official holiday dates were only confirmed in early November. Asking them now gives you the most time to plan your orders around their answers.

When do Chinese factories close for Chinese New Year 2027?

Chinese factories are usually affected for much longer than the nine-day public holiday. Output often starts to drop three to four weeks before it, and it can take four to six weeks from the start of the holiday for production to return to normal.

The table below shows the likely timeline for 2027 (SEKO Logistics, 6 August 2026).

Estimated timeline of Chinese factory slowdown, shutdown and recovery around Chinese New Year 2027
StageApproximate timingWhat to expect
SlowdownFrom around 9 to 16 JanuaryOutput falls as workers start travelling home
ShutdownAround 30 January to 14 FebruaryMost factories are closed
RestartAround 20 February to 6 MarchFactories reopen, often with around 35% of their workforce
Full recoveryAround 6 to 20 MarchOutput back to normal for most factories

These dates are estimates, published before China confirmed its holiday dates. Each factory sets its own timetable, so the dates your suppliers give you are the ones to plan your production around.

Why do the delays last longer than the shutdown?

Many factory workers travel long distances home for the holiday. More than 300 million migrant workers make the journey each year, and they return over several weeks rather than all at once (DHL, 5 March 2026).

Some extend their leave, and some move to new jobs. Up to 25% of factory workers may not return to their previous employer, so factories often need to recruit and train new staff (SEKO Logistics, 6 August 2026).

After the 2026 holiday, factories ran at around 30 to 35% of capacity at the end of February, 50 to 60% in early March and 80 to 90% by mid-March. Most were back to full output by late March (DHL, 5 March 2026).

For your production line, the wait doesn't end when the factory reopens. Parts usually take three to four weeks to make, then around eight weeks to reach the UK by sea. That means:

  • Parts shipped just before the shutdown may not arrive until late March or early April.
  • Parts ordered in March, once factories are running normally again, may not arrive until late May at the earliest.

When should you order from China before Chinese New Year 2027?

For standard orders, freight specialists advised UK importers to place purchase orders by October 2026, so production could finish by early December. If you haven't ordered yet, ask each supplier for its closing dates now, book freight for December or January, and allow extra time for shipping.

This is the timeline SEKO Logistics suggests for UK importers (SEKO Logistics, 28 October 2026).

  • Complex or custom orders: August to September 2026
  • Standard orders: September to October 2026
  • Production finished: late November to early December 2026
  • Freight booked: December 2026 to January 2027
  • Goods leave port: January 2027

If you've missed these windows, SEKO's advice is to confirm each supplier's closing and reopening dates and secure freight for December and January. It also suggests booking freight at least three weeks before your goods are ready, and adding one to two weeks to your usual time at sea.

What should you check before Christmas?

Start with the parts that would stop a build if they arrived late. Then check when each supplier closes, when it's back at full output, and whether your stock will last until new orders can reach you. It's worth planning for both Q1 and Q2 of 2027, not just Q1.

  1. Your parts list: which parts for your builds up to June come from Asia, and which would stop production?
  2. Supplier dates: when does each supplier close, and when are they back at full output?
  3. Ex-factory dates and freight: when will your goods be ready to leave, and is freight booked?
  4. Stock cover: will your stock last until new orders can reach you, possibly not until late May?
  5. Your own Christmas closure: who will receive deliveries and chase orders in the first days of January?

What can you do if timings look tight?

The main options are to bring forward orders for your most critical parts, hold extra stock, or send the most urgent items by air. Each one adds cost, so it makes sense to focus on the parts that would stop production.

  • Bring forward orders: order critical parts now, even if that means ordering more than usual.
  • Hold extra stock: safety stock, the extra parts you keep on top of what you expect to use, covers you if a delivery is late. Our article on the September 2026 PMI and safety stock shows a simple way to work it out.
  • Split the shipment: send the most urgent parts by air and the rest by sea. Air freight is faster, but it costs more.
  • Find a second source: for critical parts, a supplier in a country less affected by the holiday, or one holding stock closer to home, can reduce the risk.

Some sourcing partners can also hold stock against your forecast, so a late delivery doesn't stop your line. Our guide to managed buffer stock explains how it works.

How long will delays last after Chinese New Year?

Supply can stay slow into the second quarter of 2027, which may affect builds planned for the spring. Factories restart with fewer staff and a backlog of orders, so new orders placed in March may take longer to make before they're even shipped.

After the 2026 holiday, lead times for orders placed in March grew from around three weeks to five or six weeks (DHL, 5 March 2026). However, sea freight rates often ease once the rush before the holiday has passed, so March can still be a sensible time to order for later in the year.

FAQs

When is Chinese New Year 2027?

Chinese New Year 2027 falls on Saturday 6 February 2027. China's official Spring Festival holiday runs for nine days, from Friday 5 to Saturday 13 February.

Why is Chinese New Year earlier in 2027?

Chinese New Year follows the lunar calendar, so its date moves each year. In 2026 it fell on 17 February, so the 2027 date is 11 days earlier.

Is Chinese New Year the same as Lunar New Year?

In most cases, yes. Lunar New Year is the wider name for the same festival, which is celebrated across East and Southeast Asia, not just in China. It's called the Spring Festival in China, Tết in Vietnam and Seollal in South Korea, and it's also a public holiday in Taiwan, Hong Kong, Singapore and Malaysia.

How long do Chinese factories close for Chinese New Year?

The official holiday in 2027 is nine days, but factories are affected for much longer. Many slow down from mid-January and may not be back to full output until March.

When will parts ordered after Chinese New Year 2027 arrive?

Parts ordered in March, once factories are running normally again, may not reach the UK until late May at the earliest. They usually take three to four weeks to make, then around eight weeks by sea.

Do factories in Vietnam and Taiwan close for Lunar New Year too?

Yes. Vietnam's official Tết holiday runs from 4 to 10 February 2027, and Taiwan's government calendar gives seven days off over the same dates. Private employers in both countries may set different dates, so it's best to check with each supplier.

Sources

Need a custom quote or specific specs?

Send us an enquiry or your component specs. We aim to come back to you quickly with pricing and lead times.